Governance - WHAT A DRAG!
FD=½CPAV2
The same principle can be applied to drag in projects, the more urgently something is needed the
greater the impact of those items that cause drag. To be clear any activity that is not directly
associated with producing the goods is a drag.
I.e. if you didn’t do them, in theory, at least, the project would still
deliver.
By far the biggest drag on a project is GOVERNANCE.
i.e., record keeping, planning, monitoring, report writing, progress updating, change
management, risk management and ATTENDING
MEETINGS. In other-words nearly everything
the project management team does and would have the wider project team do (that
is not actually expending effort producing the goods).
ANALOGY: Germ Theory1 Louis
Pasteur:
“Medicine had been „successfully‟ practised without the knowledge of
germs. In a pre-germ theory paradigm,
some patients got better, some got worse and some stayed the same; in each
case, some rationale could be used to explain the outcome..”
Louis Pasteur hypothised that germs were a significant cause of post
operative deaths. Whilst the patient
would almost certainly die without surgery, without good hygiene, they would
probably not get better (and probably die).
Hertzberg later applied the same principles to his Two Factor Theory of
Emotion2. AKA Motivation/Hygiene Theory
Governance, in project management terms is, in
Hertzbergian terms a hygiene factor in that it contributes little to the
outcome, but has a significant impact on the chances of failure.
FACT: Without governance projects are highly likely to fail (unproven)
So, there is a dichotomy - GOVERNANCE
causes DRAG, slowing and adding risk to the
project, but the project needs GOVERNANCE to
assure SUCCESS!
SOLUTION: Minimum Viable Governance or
MVG
The objective of a MVG model is to apply no more governance than required
for the project to achieve its goals with reasonable certainty. (i.e. sufficiently
assure against failure)
Defining the level, breadth and depth of governance required to meet this
objective requires a good understanding of a number of, often confounding variables
and factors including:
- Duration of the project
- Scale and complexity of the project
- Number of stakeholders
- Demographic and geographic spread of stakeholders
- Size of project teams
- Make of project teams
- Politics within the project
- Politics surrounding the project
- Public or private organisations
- Governed or non-governed organisations
- Type of products to be delivered
- Certainty of outcomes
- Clarity of objectives or vision
- Likelihood of change throughout the project lifecycle
One should also look at what the project governance is intended to achieve. This can range from simple delivery assurance,
through risk mitigation/reduction, command & control, compliance to pure totalitarianism. The latter serving only to assuage the sponsors’
paranoia.
It is incumbent on responsible project and programme management professionals
to apply no more governance than is absolutely necessary to the projects under their
leadership. To do otherwise, risks governance
for the sake of governance only which is likely to alienate project managemet from delivery teams and
stakeholders alike, adding more drag and further reducing the likelihood of success.
However, successfully achieving MVG, is not an easy task and takes both effort
and experience. In the long term,
however, the investment almost always pays off.
TIPS & TRICKS Tailoring the governance to fit.
1. PURPOSE: Look at the purpose of each element of project
governance and ask “why are we doing this?”
If there is no clear purpose or the answer is “because the text-book [APM, PMI, PRINCE2 etc etc] says we should” – don’t do it!
2. OUTCOME: If the purpose
is understood, then look at and agree the outcome required – from this the [minimum]
breadth and depth can be easily understood and agreed
3. CERTAINTY & VOLATILITY: The more certain the outcome, how well the requirements
are understood and how likely they are to change the less monitoring, management
and control is needed. The reverse is true,
in highly volatile situations where the external landscape may be changing or in
an agile “build fast/fail fast” environment – it’s essential that changes are communicated
and recorded in detail.
4. POLITICS: Always a touchy subject, but the more politically
questionable the environment (i.e. motives and morals of stakeholders) the greater
the need to protect the entire project team from “poor recollection” or “altered
facts”.
If you would like to know more click here https://www.cjshelton.co.uk/contact-chris
AGILE: It should be noted that whilst
the Agile Manifesto espouses:
- Individuals and interactions over processes and tools
- Working software over comprehensive documentation
- Customer collaboration over contract negotiation
- Responding to change over following a plan
§
It DOES NOT negate the need for a level of governance, far from it, agile projects frequently need higher quality governance than that of a traditional (waterfall/turnkey) project.
NOTES:
1.
Pasteur, Louis (3 May
1880). Translated by H.C. Ernst. "Extension Of The Germ Theory To
The Etiology Of Certain Common Disease". Comptes rendus de l'Académie des Sciences. French Academy of Sciences. 90: 1033–44 – via Fordham University Modern History Sourcebook.
2. "Herzberg's Motivation-Hygiene Theory: Two-factor". Education Library. 2021-03-31. Retrieved 2021-03-31.
Comments
Post a Comment